Merit Gov requirements report

Prepared for plan start 2026-11-20 from attachment_j1_help_desk_pws.md, sample_sow.docx.

The short version

  • 37 contractor obligations found in 2 documents: 13 requirements, 9 deliverables, 4 reporting items, 9 security items, 2 prohibitions. 3 Government responsibilities listed separately.
  • 6 deliverables due in the next 30 days (by 2026-12-20). First up: Weekly ticket aging report on 2026-11-27.
  • Compliance frameworks named: ATO, FISMA, FedRAMP, NIST SP 800-171, NIST SP 800-53, NIST SP 800-88, Section 508, WCAG; plus 4 FAR/DFARS clauses cited.
  • Redacted 15 pieces of personal information (1 Social Security number, 3 email addresses, 3 phone numbers, 1 date of birth, 2 street addresses, 5 names). Keep pii_map_KEEP_PRIVATE.csv out of AI tools, email and shared drives.
  • Schedule: 50% of finished tasks were on time (2 of 4); 1 open task past due (worst: T-021, 5 days late).

Obligations found

Every sentence that commits the contractor (shall, must, will provide/deliver/submit/maintain/ensure/perform/support, is required to, responsible for) is one row in obligations.csv. 15 obligations mention a deliverable (deliver, submit, report, plan, document).

Type Count
Requirement 13
Deliverable 9
Reporting 4
Security 9
Prohibition 2
Government responsibility (not your task) 3

Deliverables due in the next 30 days (through 2026-12-20)

Due Task Deliverable Owner Rule Source
2026-11-27 T-005 Weekly ticket aging report Project manager Weekly attachment_j1_help_desk_pws.md PWS 2.3 Reporting
2026-11-27 T-032 Weekly Ticket Metrics Project manager Weekly sample_sow.docx 4. Deliverables
2026-12-05 T-010 Transition-In Plan Project manager within 15 calendar days after award sample_sow.docx 3.1.2
2026-12-18 T-030 Project Management Plan Project manager Within 20 business days after award sample_sow.docx 4. Deliverables
2026-12-20 T-016 Monthly Service Desk Report Project manager Monthly; no later than the 10th business day of each month sample_sow.docx 3.2 Service Desk Support
2026-12-20 T-031 Monthly Status Report Project manager Monthly sample_sow.docx 4. Deliverables

Dates count from 2026-11-20 as the award/start date. Business days skip weekends but not federal holidays. Recurring items show their first occurrence.

Draft work plan

37 tasks in work_plan.csv, one per contractor obligation, grouped into phases. A deliverable is linked to up to 3 earlier tasks in its section, and anything 'after approval of' another deliverable is linked to that deliverable's task.

Phase Tasks Main owners
Transition-in 4 Project manager (3), ISSO / security lead (1)
Delivery 21 ISSO / security lead (8), Service desk lead (7), Data engineer (2)
Reporting 10 Project manager (9), ISSO / security lead (1)
Closeout 2 ISSO / security lead (1), Project manager (1)

Transition-in:

Task What to do Owner Due Depends on
T-009 Conduct a kickoff meeting with the COR within 10 business days after contract award Project manager 2026-12-04 -
T-010 Submit a Transition-In Plan within 15 calendar days after award Project manager 2026-12-05 T-009
T-011 Complete onboarding of all key personnel, including background investigation forms, within thirty (30) days of... ISSO / security lead 2026-12-20 -
T-030 Deliver Project Management Plan Project manager 2026-12-18 -

Delivery:

Task What to do Owner Due Depends on
T-001 Maintain an average speed to answer of 60 seconds or less for all help desk calls Service desk lead - -
T-002 Staff the help desk with at least four Tier 1 analysts during core hours Service desk lead - -
T-003 Maintain the help desk knowledge base Service desk lead - -
T-007 Retain ticket records for three years in accordance with NARA guidance Service desk lead - -
T-008 Do not store FEA records on personal devices Project manager - -
T-012 Provide Tier 1 and Tier 2 help desk support from 7:00 a.m. to 7:00 p.m. Eastern Time, Monday through Friday Service desk lead - -
T-013 Respond to priority 1 incidents within 1 hour of notification Service desk lead within 1 hour of notification -
T-014 Resolve 80 percent of Tier 1 tickets on first contact Service desk lead - -
T-015 Do not disclose ticket data containing personally identifiable information to any third party ISSO / security lead - -
T-017 Host the FEA case management application in a FedRAMP Moderate authorized cloud environment ISSO / security lead - -
T-018 Maintain 99.9 percent availability for all production hosting infrastructure, excluding scheduled maintenance windows Cloud engineer - -
T-019 Perform database backups daily and test restoration quarterly Data engineer 2026-11-21 -
T-020 Comply with FISMA and implement security controls in accordance with NIST SP 800-53 Rev. 5 at the moderate baseline ISSO / security lead - -
T-021 Deliver a System Security Plan (SSP) within 45 days after contract award to support the Authority to Operate (ATO) ISSO / security lead 2027-01-04 T-020
T-023 Ensure all contractor personnel complete annual security awareness training ISSO / security lead 2027-11-20 -
T-024 Report all suspected security incidents to the FEA Security Operations Center within 1 hour of discovery ISSO / security lead within 1 hour of discovery -
T-025 Ensure contractor systems that process controlled unclassified information meet NIST SP 800-171 and DFARS... ISSO / security lead - -
T-026 Keep this record in a locked file ISSO / security lead - -
T-027 Ensure all software and electronic content delivered under this SOW conform to Section 508 of the Rehabilitation Act... Accessibility lead - -
T-028 Develop and deliver end-user training on the new case management application to up to 300 FEA staff Training lead - -
T-029 Migrate legacy case records from the on-premises database to the cloud environment no later than March 31, 2027 Data engineer 2027-03-31 -

Reporting:

Task What to do Owner Due Depends on
T-004 Deliver a knowledge base quality review annually Project manager 2027-11-20 T-003
T-005 Provide a weekly ticket aging report, delivered each Monday Project manager 2026-11-27 -
T-006 Provide a customer satisfaction survey summary within 5 business days after the end of each quarter Project manager 2027-02-18 T-005
T-016 Submit a Monthly Service Desk Report no later than the 10th business day of each month Project manager 2026-12-20 T-013 T-014 T-015
T-022 Submit a Plan of Action and Milestones (POA&M) update quarterly ISSO / security lead 2027-02-18 T-020 T-021
T-031 Deliver Monthly Status Report Project manager 2026-12-20 T-030
T-032 Deliver Weekly Ticket Metrics Project manager 2026-11-27 T-030 T-031
T-033 Attend a weekly status meeting with the COR Project manager 2026-11-27 -
T-034 Provide a quarterly program review briefing to FEA leadership Project manager 2027-02-18 T-033
T-035 Provide an annual customer satisfaction survey summary Project manager 2027-11-20 T-033 T-034

Closeout:

Task What to do Owner Due Depends on
T-036 Submit a Transition-Out Plan no later than 90 calendar days before the end of the period of performance Project manager 2027-07-02 -
T-037 Return all Government-furnished equipment and sanitize all Government data in accordance with NIST SP 800-88 within... ISSO / security lead within 30 days after contract completion -

Response times and event-driven deadlines

These have a deadline tied to an event (an incident, a request, the end of the contract) rather than a calendar date. Build them into your procedures and alerts.

Task What to do Deadline rule Owner
T-013 Respond to priority 1 incidents within 1 hour of notification within 1 hour of notification Service desk lead
T-024 Report all suspected security incidents to the FEA Security Operations Center within 1 hour of discovery within 1 hour of discovery ISSO / security lead
T-037 Return all Government-furnished equipment and sanitize all Government data in accordance with NIST SP 800-88 within... within 30 days after contract completion ISSO / security lead

Compliance frameworks and clauses

Framework or clause Obligations Obligation IDs Paragraphs mentioning
ATO 1 OBL-021 1
DFARS 252.204-7012 1 OBL-025 2
FISMA 1 OBL-020 1
FedRAMP 1 OBL-017 1
NIST SP 800-171 1 OBL-025 1
NIST SP 800-53 1 OBL-020 1
NIST SP 800-88 1 OBL-037 1
Section 508 1 OBL-027 1
WCAG 1 OBL-027 1
FAR 52.204-21 0 1
FAR 52.224-3 0 1
FAR 52.239-1 0 1

A framework can be named in a clause list without any obligation sentence pointing at it; those show 0 obligations but still apply.

What the Government has committed to

Not your tasks, but your schedule may depend on them. Track them and raise delays with the COR in writing.

ID Section Commitment Due
GOV-001 PWS 2.4 Definitions The Government will provide office space for two on-site analysts at [ADDRESS-1]. -
GOV-002 5. Government Responsibilities The Government shall provide the contractor with remote access to the FEA network and necessary system accounts within 10 business days after award. 2026-12-04
GOV-003 5. Government Responsibilities The COR will provide written comments on each deliverable within 10 business days of receipt. within 10 business days of receipt

Personal information redacted

Type Distinct items Times redacted
Social Security numbers 1 1
Email addresses 3 3
Phone numbers 3 3
Dates of birth 1 1
Street addresses 2 2
Personal names 5 5

pii_map_KEEP_PRIVATE.csv links every token back to the real value. Do not paste it into ChatGPT, Claude or any other AI tool, do not email it, and do not store it next to the redacted copies. Share the files in redacted/ instead.

We look for SSNs (###-##-####), email addresses, US phone numbers, dates of birth next to DOB or date of birth, street addresses, and names after Mr./Ms./Mrs./Dr. or after POC:, Contracting Officer:, COR: or Name:. Names written any other way are not caught: skim the redacted copy before sharing it.

Schedule variance

8 tracker rows read, 7 matched to the work plan; 50% of finished tasks on time (2 of 4); late finishes averaged 3.5 days; 1 open task past due.

Task Tracker title Status Due Days late
T-021 System Security Plan In Progress 2026-11-15 5

Finished late:

Task Tracker title Due Completed Days late
T-010 T-010 Submit Transition-In Plan 2026-10-16 2026-10-20 4
T-011 Complete onboarding of key personnel and background investigation forms 2026-10-31 2026-11-03 3

1 tracker row did not match any work plan task (see variance.csv). Put the T-### task ID in the title or a label to match exactly.

30 work plan tasks have no matching tracker item: T-001 T-002 T-003 T-004 T-005 T-006 T-007 T-008 T-012 T-013 T-014 T-015 T-017 T-018 T-019 T-020 T-022 T-023 T-024 T-025 T-026 T-027 T-028 T-030 T-031 T-032 T-034 T-035 T-036 T-037. Each one is an obligation nobody is tracking yet.

What we read

File Type Paragraphs and table rows Sentences Obligations Government items
attachment_j1_help_desk_pws.md Markdown 10 14 8 1
sample_sow.docx Word 37 38 29 2
  • Period of performance found: 2026-10-01 to 2027-09-30; used for 'days before the end of the period of performance' deadlines.
  • jira_export.csv: 8 task rows read, 1 exact duplicate row(s) dropped, 1 row(s) had a date we could not read (treated as blank)

Limits

Obligations are found by keywords, not by reading for meaning: check conditional or cross-referenced requirements in the source, and treat the work plan, owners and dates as a first draft. Dates assume 2026-11-20 is the award/start date. Legacy .doc and PDF files are not read; save them as .docx.